Schisler Road (Regional Road 27) Bridge Rehabilitation
All Niagara Region projects

About the Project

The Schisler Road Bridge is located in the rural area of the City of Niagara Falls and currently has two lanes. The bridge provides a main crossing of the Canadian Pacific Railway main line track.

This project will carry out recommendations from a bridge condition survey that was conducted in 2019, extending its service life.

Businesses remain open

  • Temporary lane, sidewalk and driveway closures may happen from time-to-time, but access to businesses will be maintained at all times.

Expected traffic delays

  • Regional traffic will be reduced to a single lane for the duration for the project. Drivers can avoid delays by using alternative routes. A full closure with detours is anticipated in late October.

Driveway access and on-street parking

  • The contractor is required to maintain access to all homes during construction. There will be occasions when residents may experience some delays, lack of service and inconvenience. Every effort will be made by the contractor to minimize these occurrences as well as communicate when they are to occur.
  • We ask that you refrain from parking on the street during construction activities, as this can cause delays and prolong the construction period.

Project Timeline

Sept. 15, 2021
Contractor onsite to mobilize

Mid Sept. 2021
Canadian Pacific Track Protection installed on bridge

Mid Sept. 2021 to late Nov. 2021
Stage #1 begins - Full lane closure of the eastbound lane to allow for bridge rehabilitation

Late Oct. 2021
Single full night closure for jacking of the bridge

Late Nov. 2021
Stage #1 - Eastbound lane complete

Late Nov. 2021 to Mid Dec. 2021
Stage #2 begins - Full lane closure of the westbound lane to allow for bridge rehabilitation

Late Dec.
Project completion

Contact

David Lampman, CET
Niagara Region
Project Manager
905-980-6000 ext. 3644
Email David Lampman

Mr. Pierre Burton, P.Eng
Associated Engineering (Ont.) Ltd.
Contract Administrator
905-346-0990
burtonp@ae.ca

Image Gallery


Rr 27 Bridge

Reports and Documents

The Schisler Road (Regional Road 27) bridge before rehabilitation.
Page Feedback Did you find what you were looking for today?