Baker Road Wastewater Treatment Plant
All Niagara Region projects

About the Project

Niagara Region, in partnership with the Town of Grimsby, the Town of Lincoln and the Township of West Lincoln, are preparing a Pollution Prevention and Control Plan as well as a Wastewater Master Servicing Plan update study.

The project's scope is to update the previous 2009 Baker Rd. Wastewater Treatment Plant Pollution Control Plan to meet the goals of the procedure F-5-5 and under the Class Environmental Assessment process for Master Plans, develop a prioritized action plan for improvements of the system supporting short and long-term growth and sustainability of the wastewater infrastructure.

This study will satisfy Phase 1 and 2 of the Municipal Engineers Association Class Environmental process (October 2000, as amended in 2007, 2011 and 2015). This is an approved process under the Ontario Environmental Assessment Act and will evaluate alternatives to help support the long-term sustainability of the wastewater systems.

Project Timeline

july 2019 - completed
Request for proposal issued

oct. 2019 - completed
Kick-off meeting

nov. 18, 2019 - completed
Technical memo #1 - background review

dec. 2, 2019 - completed
Technical memo #2 - flow monitoring program review, assessment and analysis

feb. 11, 2020 - completed
Technical memo #3 - hydraulic sewer model review and recommendations

feb. 11, 2020 - completed
Technical memo #4 - gap analysis

sept. 25, 2020 - completed
Technical memo #5A - hydraulic modeling development

oct. 2, 2020 - completed
Technical memo #5B - flow monitoring stretch of time in two municipalities

nov. 2, 2020
Technical memo #5C - baseline system performance and growth analysis

nov. 9, 2020
Technical memo #6A - evaluation criteria

dec. 18, 2020
Review of evaluation criteria

Q1 2021
Individual workshops with Grimsnby, Lincoln and West Lincoln

May 2021
Preliminary growth data with Planning and Development

July 2021
Workshops with Grimsby, Lincoln and West Lincoln - planning for growth

Aug. 25 - Sept. 8, 2021 - completed
Public Information Centre #1

September 2021
Draft Pollution Prevention and Control Plan Report

December 2021
Council report

Contact

Ilija Stetic, B.Sc, PMP
Project Manager
905-980-6000 ext. 3777
Email Ilija Stetic