RoadLocationStatus
Bridge / Structure Rehabilitation
Burgoyne Bridge
St. Catharines
RR 81 over 12 Mile Creek and Hwy. 406
Construction underway
Reece Bridge
West Lincoln
RR 69 over Twenty Mile Creek
Construction underway
Ontario Power Generation (OPG) Bridges
Thorold
RR 67 and RR 50 over Gibson Lake
Completed
Central Avenue Bridge
Fort Erie
RR 124 over Canadian National Railway tracks
Completed
Glenridge Ave. Bridge
St. Catharines
RR 50 over Canadian National Railway tracks
Completed
East Main St. Bridge
Welland
RR 27 over the tracks (west of RR 84 Doans Ridge Rd.)
Under design
Niagara St. Bridge
Welland
RR 50 over the Welland River
Under design
St. Paul St. West Canadian National Railway Bridge
St. Catharines
RR 81 over Canadian National Railway track
Under design
Burgoyne Bridge
St. Catharines
Regional Road 81 over 12 Mile Creek to Hwy. 406
Under design
Reece Bridge
West Lincoln
Regional Road 69 over 20 Mile Creek
Study in progress
Beechwood Bridge
Niagara Falls
Regional Road 70 over Canadian National Railway
Under design
Ontario Power Generation Bridges
Thorold
Regional Road 67 and Regional Road 50 over Gibson Lake
Under design
Central Ave Bridge
Fort Erie
Regional Road 124 over Canadian National Railway Tracks
Study in progress
Main St. Bridge
Fort Erie, Welland
Regional Road 27 over Welland Canal
Under design
Bowen Rd. Bridge
Fort Erie
Bowen Rd. at QEW
Study in progress
RoadLocationStatus
Intersection Improvement
Geneva St. / Niagara St. / Church St.
St. Catharines
Under design
Falls Ave.
Niagara Falls
at Bender St.
Under design
King St.
Lincoln
Roundabout at Durham Rd. and Greenlane Rd.
Completed
Regional Road 20
West Lincoln
Industrial Park Rd. to South Grimsby Road 6
Completed
Regional Road 20
West Lincoln
South Grimsby Road 6 to Wade Rd.
Under design
Lundy's Ln.
Niagara Falls
Garner Rd.
Construction underway
St. Paul St. W
St. Catharines
Vansickle Rd.
Under design
Regional Rd. 20
West Lincoln
Industrial Park Rd. to South Grimsby Rd. 6
Study in progress
Falls Ave.
Niagara Falls
Bender St.
Under design
King St.
Lincoln
Roundabout at Durham Rd. and Greenlane Rd.
Construction underway
Regional Rd. 20
West Lincoln
South Grimsby Rd. 6 to Wade Rd.
Under design
St. Paul St. West
St. Catharines
Vansickle Rd. and First St. Louth
Under design
Niagara Stone Rd.
Niagara-on-the-Lake
Concession 6
Under design
Lundy's Lane
Niagara Falls
Kalar Rd.
Construction underway
Regional Road 20
Grimsby
Industrial Park Rd. to South Grimsby Rd. 6
Study in progress
Lundy's Lane
Niagara Falls
Highland Ave. to Main St.
Construction underway
Niagara Stone Rd.
Niagara-on-the-Lake
Airport Rd. to Line 2
Study in progress
Main St.
Grimsby
Cabernet St. to Iroquois Trail
Construction underway
Niagara Stone Rd.
Niagara-on-the-Lake
Hunter Rd.
Under design
RoadLocationStatus
Rehabilitation / Reconstruction
Smithville Rd.
West Lincoln
South Chippawa Rd. to Concession Rd. 2
Study in progress
St. Paul St. West
St. Catharines
Ninth St. to Seventh St.
Under design
Lakeshore Rd.
Niagara-on-the-Lake
Townline Rd. to Four Mile Creek
Study in progress
Glendale Ave.
St. Catharines
Canadian National Railway to Canal Park
Construction underway
Niagara St.
St. Catharines
Vine St. to Carlton St.
Under design
Old Hwy. 20
Pelham
Pelham to Haist St.
Under design
Glendale Ave.
St. Catharines
Jacobson Ave. to Hwy. 406
Study in progress
Lakeshore Rd.
St. Catharines
Geneva to Bradmon Dr.
Construction underway
Lakeshore Rd.
St. Catharines
Lakeport Rd. to Lake St.
Under design
Old Hwy. 20
Pelham
Lookout to Haist St.
Study in progress
Main St.
St. Catharines
Third St. to Henley Ave.
Under design
Killaly St. West
Port Colborne
King St. to Steele St.
Under design
Stanley Ave.
Niagara Falls
Thorold Stone Rd. to Whirpool Rd.
Under design
Stanley Ave.
Niagara Falls
Thorold Stone Rd. to Valley Way
Under design
Canborough Rd.
West Lincoln
Townline Rd. to Regional Road 20
Under design
Lakeshore Rd.
St. Catharines
Lake St. to Geneva and Bradmon
Under design
Lakeshore Rd. West
Fort Erie, St. Catharines
Third St. to Seventh St.
Under design
St. David's Rd.
Thorold
Merrittville Hwy. to Hwy. 406
Study in progress
Canborough Rd.
West Lincoln
Baldwin Rd. to Coffey Bridge
Under design
Old Hwy. 8
Lincoln
Vinehaven Trail to Twenty Third St.
Study in progress
Welland Ave.
St. Catharines
Niagara St. to QEW
Construction underway
Mountain Rd.
Niagara Falls
Taylor Rd. to Kalar Rd.
Construction underway
Mountain Rd.
Niagara Falls
Kalar Rd. to Dorchester Rd.
Construction underway
Pelham Rd.
St. Catharines
First St. to Effingham Rd.
Construction underway
RoadLocationStatus
Road Expansion
Thorold Stone Rd.
Niagara Falls
Stanley Ave. to Gale Centre
Completed
Montrose Rd.
Niagara Falls
Charnwood Ave. to McLeod Rd.
Under design
McLeod Rd. (Phase 1)
Niagara Falls
Pin Oak Dr. to Hydro Canal
Under design
McLeod Rd. (Phase 2)
Niagara Falls
Hydro Canal to Wilson Cres.
Under design
Martindale Rd.
St. Catharines
Fourth Ave. to QEW
Under design
Livingston Ave.
Grimsby
Casablanca Blvd. to Main St.
Study in progress
Casablanca Blvd.
Grimsby
Livingston Ave. to QEW
Study in progress
Niagara Stone Rd.
Niagara-on-the-Lake
Concession 6 Rd. to East / West Line
Under design
Glendale Ave.
Niagara-on-the-Lake
Homer Rd. to Niagara on the Green
Completed
Rice Rd.
Pelham
Old Hwy. 20 to Port Robinson Rd.
Under design
Thorold Stone Rd.
Niagara Falls
Stanley Ave. to Gale Centre
Construction underway
McLeod Rd.
Niagara Falls
Pin Oak Dr. to Hydro Canal
Under design
McLeod Rd.
Niagara Falls
Hydro Canal to Wilson Cres.
Under design
South Niagara E/W Arterial
Region
To Be Determined
Study in progress
Hwy. 406 Interchange
St. Catharines
Third St. Louth
Study in progress
Martindale Rd.
St. Catharines
Fourth Ave. to QEW
Under design
Livingston Ave.
Grimsby
Casablanca Blvd. to Main St. / Oaks Rd.
Study in progress
Casablanca Blvd.
Grimsby
Livingston Ave. to QEW
Study in progress
Niagara Stone Rd.
Niagara-on-the-Lake
Penner to East / West Line
Under design
Gelndale Ave.
Niagara-on-the-Lake
Homer Rd. to Niagara on the Green
Under design
Gelndale Ave.
Niagara-on-the-Lake
Interchange at QEW
Study in progress
Rice Rd.
Pelham
Old Hwy. 20 to Port Robinson Rd.
Under design
Thorold Stone Rd.
Niagara Falls
Stanley Ave. to Gale Centre
Under design
McLeod Rd.
Niagara Falls
Pin Oak Dr. to Hydro Canal
Under design
South Niagara Arterial Road
Fort Erie, Port Colborne, Wainfleet, Welland
Study in progress
New Escarpment Crossing
Grimsby, Lincoln
Study in progress
Hwy. 406 Interchange
St. Catharines
First St. and Third St.
Study in progress
Martindale Rd.
St. Catharines
Elderwood to QEW
Study in progress
Livingston Ave.
Grimsby
Casablanca Blvd. to Main St./Oaks rd.
Study in progress
Casablanca Blvd.
Grimsby
Livingston Rd. to QEW
Study in progress
Niagara Stone Rd.
Niagara-on-the-Lake
Virgil Rd. to East/West Line
Study in progress
Fourth Ave.
St. Catharines
Hwy 406 to Third St. Louth
Construction underway
Niagara St.
Welland
Quaker Rd. to Woodlawn Rd.
Under design
Old Hwy. 20
Pelham
Station St. to Rice Rd.
Under design
Woodlawn Rd.
Welland
First Ave. to Rice Rd.
Under design
Glendale Ave.
Niagara-on-the-Lake
Interchange modifications at QEW
Study in progress
RoadLocationStatus
Road Rehabilitation / Reconstruction
Niagara St.
St. Catharines
Carlton St. to Scott St.
Study in progress
Main St.
St. Catharines
Locke St. to Anne St.
Study in progress
Effingham St.
Pelham
Webber Rd. to River Rd.
Under design
Pelham Rd. (Phase 2)
Lincoln, St. Catharines
Effingham Rd. to Wessel Dr.
Construction underway
Canboro Rd.
West Lincoln
South Chippawa Rd. to Concession 2 Rd.
Construction underway
Old Hwy. 8
Fort Erie, Lincoln
Vinehaven Trail to Twenty Third St.
Study in progress
Mountain Rd.
Lincoln
Hillside Dr. to King St.
Completed
Lakeshore Rd.
Niagara-on-the-Lake
Townline Rd. to Four Mile Creek Rd.
Under design
Glendale Ave.
St. Catharines
Jacobsen Ave. to Burleigh Hill Dr.
Construction underway
Glendale Ave.
St. Catharines
Welland Canal to Homer Rd.
Under design
Lakeshore Rd. (Phase 3)
St. Catharines
Lake St. to Geneva St. / Bradmon Dr. to O’Mara Dr.
Construction underway
Lakeshore Rd.
St. Catharines
Third St. to Seventh St.
Under design
Canborough Rd.
West Lincoln
Wellandport Rd. to Community Centre
Under design
Canborough Rd.
West Lincoln
Baldwin Rd. to Coffey Bridge
Under design
York Rd.
Niagara-on-the-Lake
RR 55 to Airport Rd.
Under design
Twenty Mile Rd.
West Lincoln
Victoria Ave. to Mountain Rd.
Under design
Pelham Rd. (Phase 3)
Lincoln
Wessell Dr. to Centre St.
Under design
Ontario St.
St. Catharines
Lakeshore Rd. to Linwell Rd.
Under design
Riverside Dr.
Welland
Prince Charles Dr. to Lincoln St.
Under design
Dominion Rd.
Fort Erie
Helena St. to Lakeshore Rd.
Under design
Dominion Rd.
Fort Erie
Burleigh Rd. to Buffalo Rd.
Construction underway
Creek Rd.
Wainfleet
RR 4 (Wellandport Rd.) to RR 62 (Canborough Rd.)
Study in progress
Main St.
Grimsby
Cabernet St. to Baker Rd. / Nelles Rd. South to Orchard Pkwy.
Study in progress
King St.
Lincoln
Durham Rd. to Lincoln Ave.
Under design
St. David’s Rd.
St. Catharines
Hwy. 406 to Burleigh Hill Dr.
Study in progress
Mountain Rd.
Lincoln
Hill Side Dr. to King St.
Completed
RoadLocationStatus
Road Resurfacing
Grimsby Rd.
Grimsby
Highway 20 to CPR Railway crossing
Under design
Queenston St.
St. Catharines
Grantham St. to Bunting Rd.
Under design
Fourth Ave.
St. Catharines
Eleventh St. to Seventh St.
Under design
South Service Road
Grimsby
Region Boundary to Casablanca Blvd.
Under design
South Service Road
Grimsby
Durham Rd. to Ontario St.
Under design
Stewart Rd.
Niagara-on-the-Lake
Niagara Stone Rd. to Carlton St.
Under design
Allanport Rd.
Thorold
Turner Rd. to Hwy. 20
Under design
Central Ave.
Fort Erie
Gilmore Rd. to Niagara Pkwy.
Under design
River Rd.
Wainfleet
Green Rd. to O’Reilly’s Rd.
Under design
Miller Rd.
Port Colborne
2nd Concession to 3rd Concession
Under design
Fly Rd.
Grimsby
Mountain Rd. to South Grimsby Rd. 6
Completed
King St.
Lincoln
Brookside Dr. to Main St.
Completed
Ontario St.
St. Catharines
Fourth Ave. to Lake St.
Completed
Townline Rd.
Niagara Falls, Thorold
Thorold Stone Rd. to Lundy’s Ln.
Completed
York Rd.
Niagara-on-the-Lake
Shepard Cres. to Niagara Pkwy.
Completed
Stewart Rd.
Niagara-on-the-Lake
Lakeshore Rd. to Carlton St.
Completed
Canborough Rd.
West Lincoln
Krick Rd. to Baldwin Rd.
Completed
Hwy. 20
Pelham
Lookout St. to Cream St.
Completed
Niagara St.
Welland
Thorold Rd. to West Main St.
Completed
Miller Rd.
Port Colborne
Doan’s Ridge Rd. to Forkes Rd.
Completed
Canboro Rd.
Thorold
Highway 406 to Welland Canal
Completed
Doan's Ridge Rd.
Welland
Miller Rd. to Netherby Rd.
Completed
Keefer Rd.
Fort Erie, Welland
Netherby Rd. to Miller Rd.
Completed
Netherby Rd.
Fort Erie
Sodom Rd.
Completed
Netherby Rd.
Fort Erie
Baker Rd. to Niagara Pkwy.
Completed
Central Ave.
Fort Erie
Queen St. to Gilmore Rd.
Completed
Twenty Mile Rd.
Lincoln
Maple St. to 8th Ave. East
Completed
McLeod Rd.
Niagara Falls
Dorchester Rd. to Stanley Ave.
Completed
Niagara Stone Rd.
Niagara-on-the-Lake
York Rd. to Airport Rd.
Completed
Airport Rd.
Niagara-on-the-Lake
York Rd. to Queenston Rd.
Completed
Merrittville Hwy.
Thorold
Canboro to Holland Rd.
Completed
Prince Charles Dr. North
Welland
Fitch St. to Thorold Rd.
Completed
Bismark Rd. East
West Lincoln
Smithville Rd. to Caistor/Townline
Completed